Phase 1: Pick the site once the substation can take the power.
A plant only gets built if it is in the RUPTL and the grid can carry its output. The technology chosen here sets the unit's carbon quota for decades.
What needs to be ready
1.1 RUPTL, substation and land status
Confirm the project is listed in the RUPTL, the target substation has capacity, and the site sits outside the state forest estate or holds a forest-use approval.
1.2 Nature and community baseline
Survey montane forest at planned wellpads, marine life at the planned intake, and fishing grounds and customary land before public consultation.
1.3 Quota scenario per technology
Cost the carbon quota for each technology option before the decision is locked. New coal plants are only allowed under exemptions, and such units may run until 2050 at the latest.
According to Energy Ministry Regulation 10/2025