Phase 1: Raw water and receiving river are chosen with the site.
A pharma plant depends on stable raw water, power that must never fail and a river that receives its effluent. Figures recorded before the plant exists become the reference for PROPER and buyer audits.
What needs to be ready
1.1 Raw water for purified water
Map the source, quality and water-use licence before the RO and distillation systems are designed.
According to Government Regulation 30/2024 and Public Works Ministry Regulation 2/2024
- Water audit
- Waste+
1.2 Receiving-river baseline
Measure active-ingredient residues upstream and downstream of the planned outfall so the plant's contribution can be isolated later.
According to WHO, 2024
- Water audit
- IoT
1.3 Environmental document screening
Secure the spatial approval (KKPR) and the document type set by Amdalnet screening, since API plants using large volumes of solvent usually need a full environmental impact assessment (AMDAL).
According to Government Regulation 28/2025